HIXON YARD QUONSET HUT

Project Type

Other Services

Location

Iron Bay, BC

Surespan, in partnership with Nch’kay, installed a 60 ft × 128 ft Britespan Apex fabric structure on a concrete block foundation at the Hixon Yard for the Eagle Mountain Pipeline Project. The scope included structural frame assembly, trusses, purlins, wind bracing, fabric enclosure, doors, ventilation components, and tie-down systems. With the site accessible only by marine transport, Surespan coordinated the road transport and barging of a 110-ton crawler crane, telehandler, aerial work platform, crew trucks, and supporting equipment required to complete the installation.